Eagle Valley - Indianapolis Power and Light

WB•Koester began work on the AESIP&L’s Combined Cycle Gas Turbine in Martinsville, IN around March of 2015. A critical path component of the project involved the installation of the facilities Circulating Water Pipe Systems.

  • Demolition of 3,000 linear FT of railroad siding

  • Excavated over 22,500 CY of soil

  • Excavation for electrical duct banks, large pipe corridors, deep electrical vaults

  • Management of site paving, finish grade, seeding, parking restoration, and fencing